Achievements

Achievement and Impacts (As of 30 June, 2011)

  • 6554 IWM installations including 878 LS IWMs provide services to 3,40,808 HHs
  • 23 IWM Electrifications provide services to 871 HHs
  • Existence of 33 Service Centres, 16 Ghatta Owner's Association and 22 Manufacturers
  • Mill users, (mainly women) drudgery reduced and time saved (2 hours per milling)
  • Majority of Mill Owners are socially exclusive ( 78% ethnic and Dalit and 22% others)
  • Reduction in operation of diesel mills reducing emission of CO2 (about 3.1 ton/SS/year; 4.9 ton/LS/year and 6.01 ton/electrification/year)
  • Addressed to fulfil MDGs: mainly poverty reduction, access to education, gender empowerment, maternal health, reduction in child mortality and better environment.

IWM Installation Status Till June 2011